Dear Campus Community,
A new project to install canopy-style solar panels in Lot N is set to begin on June 9th, and will consist of several phases over the next year. Phase 1 will consist of the full closure of Parking Lot N to allow for construction activities to begin. This project will include perimeter fencing of the entire parking lot to close public access, clearing of vegetation, limited trenching, and installation of structural steel. Please see below for disruption information for this project.
Please refer to the disruption map.
Areas affected by Phase 1 of Construction:
- Phase 1 is scheduled to begin on June 9, 2026, and end by August 17, 2026.
- No parking access will be available in Parking Lot N from June 9 to August 17, 2026.
- The East and West entrances and exits will remain open but should only be used for access to HVAC Central Plan and ADA parking. Access to parking structures will remain open.
- Accessible parking spaces north of the Center for Global Innovation building will be closed. Alternative accessible parking is available north of College of Education and in Parking Structure East.
- Access to Electric Vehicle charging in Lot N will be limited to (6) six stalls adjacent to the temporary office buildings. Additional EV charging is available in the parking structures, Lot C and Lot D.
- Campus Circle will always remain open.
- The SSD cart path is not impacted by this phase of the project.
- Signage will be posted on site for any re-routing. Please exercise caution when in proximity to the construction site and follow all the posted signage.
Please reference the disruption plan for this project. The Disruption Plan highlights pedestrian paths, vehicular paths, and construction fencing for this project. Further construction notices will be shared as the project progresses, see the campus disruptions website at: https://www.csusb.edu/facilities-planning-management/campus-disruptions
Please direct any questions to Royal Hoang, Project Manager, Facilities Planning, Design and Construction, via email at royal.hoang@csusb.edu, or via phone at 949-836-7703.
Thank you,
Facilities Planning, Design and Construction