Campus Construction
Laydown areas
Admin HVAC Crane operation
Admin HVAC May 1 to Spring 2027
BA to LA Tunnel Project May 10 to early Fall 2026
EAMES T & T improvement July 1 2026 to June 2027
Fill Dirt Storage - Tunnel Project May 1 2026-Oct 2026
Fine Arts Window replacement mid May-October 2026
Generator Install - July/August 2026
HVAC Chiller Admin April 27-End of June 2026
LA room remodel
PA Project Oct 2025- April 2027
PS basement remodel April 1 - November 2026
Pharmacy Remodel May 2026
Sidewalk Replacement - summer 2026
Sprinkler Replacement July 1 2026 to Nov 2026